Skip to main content
City Logo
File #: 24-1946    Name:
Type: Consent Item Status: Agenda Ready
File created: 12/5/2024 In control: City Council
On agenda: 12/17/2024 Final action:
Title: APPROVE PLANS AND SPECIFICATIONS FOR THE RESIDENTIAL STREET REHABILITATION PROJECT, JOB NO. 40190, AND AUTHORIZE THE CITY CLERK TO ADVERTISE THE PROJECT FOR COMPETITIVE BIDS
Attachments: 1. Administrative Report, 2. Residential Street Rehabiliation 2022 (20241206)
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

To:                                                               MAYOR AND CITY COUNCIL

From:                                                               ANDREW WINJE, PUBLIC WORKS DIRECTOR

 

TITLE

title    

APPROVE PLANS AND SPECIFICATIONS FOR THE RESIDENTIAL STREET REHABILITATION PROJECT, JOB NO. 40190, AND AUTHORIZE THE CITY CLERK TO ADVERTISE THE PROJECT FOR COMPETITIVE BIDS

end

 

EXECUTIVE SUMMARY

The Residential Street Rehabilitation Project (Project), Job No. 40190, is a multi-year capital improvement program intended to maintain and improve the pavement condition of the City’s residential streets.  The next phase of the program is scheduled to rehabilitate certain streets in Districts 4 & 5 (see the attached map), and was determined by the tri-annual pavement management system report and included in the Fiscal Year 2024-25 CIP Budget.  Funding for the planned streets comes from three CIP sources 1) the ongoing/annual residential street rehabilitation program, 2) the next portion of the one-time deferred maintenance allocation (split over multiple projects), and 3) the alleyway resurfacing program, which is limited to alleys with a Pavement Condition Index (PCI) rating of 25 or less.

 

The plans and specifications for the Project are ready for competitive bidding and are available for review at the Plans and Specifications Review Area located behind the Engineering permit counter at City Hall.  The Engineer’s estimate for construction of the Project is $3,000,000, with a total project cost estimate of $3,900,000, including contingency and the costs for construction management and inspection.  Construction is expected to begin in the spring of 2025 and take approximately 100 working days to complete.  The Project is fully funded, assuming construction bids are received according to estimates.  

 

BACKGROUND

The Residential Street Rehabilitation Project is an on-going Capital Improvement Program that resurfaces and repairs residential streets.  The annual implementation of the program increases the life of the existing pavement and improves the ride of the City’s streets.  This program supports the City’s Strategic Plan goal to Invest in the City’s Infrastructure.

 

The City is required to conduct a pavement condition survey every three years in order to meet the reporting requirements of GASB 34 and to qualify for use of Proposition C and Measure R Local Return funding for rehabilitation of City streets.  In 2020, the streets were surveyed Citywide.  On September 15, 2020, the City Council discussed the Citywide Pavement Management System (PMS) Report and approved the residential streets that were recommended to be treated over the next few years with the goal to increase the City’s overall PCI to 75.  The Project includes the streets selected for the second phase of the PMS report.  The streets identified in the third phase of the Report are currently in design and the associated Project is expected to be brought for Council consideration of approval in April 2025.

 

To minimize construction costs and disruption to residents, two deferred maintenance streets and an alley identified by Council that are near the selected residential streets and/or require the same rehabilitation methods have been added to the Project solicitation.  The deferred maintenance streets include Johnston and Gibson.  The alley is east of McBain Avenue, between Manhattan Beach Blvd and Beland Blvd.

 

The plans and specifications for the Residential Street Rehabilitation Project are fully prepared and are ready for competitive bidding.  The solicitation process, if approved, should be complete in January 2025 with an anticipated contract award shortly thereafter.  Construction of the project is expected to begin in March 2025 and last roughly 100 working days.

 

COORDINATION

The Project has been coordinated by the Public Works Department.

 

FISCAL IMPACT

The Engineer’s construction cost estimate for the project is $3,000,000.  Additional soft costs bring the project total to $3,900,000, which is within the FY 2024-25 CIP amount of approved funding.

 

Funding

Amount

 

Expenditures

Amount

Residential Street Rehab #40190

$3,482,500

 

Constr. Estimate

$ 3,000,000

Residential Deferred Maintenance #41300

$361,250

 

Contingency (10%)

$   300,000

 Alleyway Resurfacing #41370

$56,250

 

Inspection and CM

$   450,000

 

 

 

Project Management

$   150,000

Total

$3,900,000

 

Total

$3,900,000

 


APPROVED BY:

Mike Witzansky, City Manager

ATTACHMENTS

                     Project Map - Residential Resurfacing Project