File #: 25-0611    Name:
Type: Consent Item Status: Agenda Ready
File created: 4/24/2025 In control: City Council
On agenda: 6/3/2025 Final action:
Title: ADOPT BY TITLE ONLY RESOLUTION NO. CC-2506-031, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF REDONDO BEACH, CALIFORNIA, AWARDING A PUBLIC WORKS CONTRACT TO SEQUEL CONTRACTORS, INC., A CALIFORNIA CORPORATION, IN THE AMOUNT OF $1,151,000 FOR THE CONSTRUCTION OF THE KINGSDALE AVENUE RESURFACING (BETWEEN GRANT AVENUE AND 182ND STREET) PROJECT, JOB NO. 40880
Attachments: 1. Administrative Report, 2. Resolution of Award, 3. Bid Results
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

To:                                                               MAYOR AND CITY COUNCIL

From:                                                               ANDREW WINJE, PUBLIC WORKS DIRECTOR

 

TITLE

title    

ADOPT BY TITLE ONLY RESOLUTION NO. CC-2506-031, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF REDONDO BEACH, CALIFORNIA, AWARDING A PUBLIC WORKS CONTRACT TO SEQUEL CONTRACTORS, INC., A CALIFORNIA CORPORATION, IN THE AMOUNT OF $1,151,000 FOR THE CONSTRUCTION OF THE KINGSDALE AVENUE RESURFACING (BETWEEN GRANT AVENUE AND 182ND STREET) PROJECT, JOB NO. 40880 

end

 

EXECUTIVE SUMMARY

The Kingsdale Avenue Resurfacing Project, Job No. 40880 (Project), is designed to rehabilitate pavement on Kingsdale Avenue from Grant Avenue to 182nd Street using a full-depth reconstruction method.  This portion of Kingsdale is a primary corridor for bus and transit vehicles, and serves several commercial properties including the South Bay Social District. 

 

On March 11, 2025, the City Council approved plans and specifications for the Project and authorized competitive bidding.  On April 24, 2025, six bids were received and publicly opened.  Following staff’s review of the bid package and confirmation of the bid tabulation, Sequel Contractors, Inc., with a bid of $1,151,000, was found to provide the lowest responsive bid. 

 

Funds for this Project are available in Capital Improvement Project (CIP), Job No. 40880. 

 

Staff recommends that City Council adopt the resolution awarding the contract for construction of the Project to Sequel Contractors, Inc. in the amount of $1,151,000.  Construction is expected to begin in the summer of 2025 and is estimated to take approximately 50 working days to complete. 

 

BACKGROUND

On December 14, 2021, the City Council approved an agreement for design of the Project to BKF Engineers.  The Project’s initial objective was to rehabilitate Kingsdale Avenue between 182nd Street and Grant Avenue through resurfacing (grind and overlay) and to repair access ramps, curbs, gutters, and drainage facilities, as necessary.  However, unexpected results during the geotechnical investigation phase identified that more extensive geotechnical work be completed as part of the project.  The extended investigation uncovered substandard pavement structure in many places that required repair.  This, coupled with the knowledge that the street serves a high volume of transit and heavy commercial vehicles, staff recommended the design include a full depth reconstruction of the entire length of the Project. 

 

On March 11, 2025, the City Council approved the final plans and specifications for the Project and authorized it to be released for competitive bidding.  On April 24, 2025, six bids were received and publicly opened with Sequel Contractors, Inc. as the apparent lowest bidder with a bid of $1,222,610.  Following staff’s review of the bid package and confirmation of the bid tabulation, Sequel Contractors, Inc.’s total bid amount was determined to be $1,151,000 based on the unit costs.  Sequel Contractors, Inc. acknowledged their computation mistake and expressed their willingness to perform the work at the lower total bid price.  As such, Sequel Contractors, Inc., with a bid of $1,151,000, was found to have provided the lowest responsive bid from a responsible bidder. 

 

COORDINATION

The development of the Project Plans and Specifications were coordinated by the Engineering Services Division of the Public Works Department.  Construction of the Project will be coordinated with the Transit Services Division of the Community Services Department to accommodate bus traffic during completion of the project. 

 

FISCAL IMPACT

Funds for the Project are available in CIP Job No. 40880.  Construction of the Project is eligible to be funded entirely by local return Proposition C funds, because Kingsdale Ave. is a dedicated bus route.

 

Funding

 

 

Estimated Expenditures

 

Kingsdale Ave Resurfacing Project #40880

$1,506,000

 

Construction Estimate of Sequel Contractors, Inc.

$ 1,151,000

 

 

 

Contingency (10%)

$   125,000

 

 

 

Constr. Mgmt./Inspection

$   115,000

 

 

 

Project Management

$   115,000

Total

$1,506,000

 

Total

$1,506,000

 


APPROVED BY:

Mike Witzansky, City Manager

ATTACHMENTS

                     Reso - No. CC-2506-031 Resolution of Award to Sequel Contractors, Inc.

                     Bid Results - Kingsdale Avenue Resurfacing Project, Job No. 40880, April 24, 2024