ADOPT BY TITLE ONLY RESOLUTION NO. CC-2606-041, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF REDONDO BEACH, CALIFORNIA, AWARDING A PUBLIC WORKS CONTRACT TO GRIFFITH COMPANY, A CALIFORNIA CORPORATION, IN THE AMOUNT OF $5,247,590 FOR FULTON PLAYFIELD MULTI-BENEFIT INFILTRATION PROJECT, JOB NO. 60280
end
EXECUTIVE SUMMARY
The Fulton Playfield Multi-Benefit Infiltration Project, Job No. 60280 (Project) is included in the updated and City Council approved Enhanced Watershed Management Program (EWMP) as a critical project. On April 21, 2026, the City Council approved the Project plans and specifications and authorized the City Clerk to advertise the Project for competitive bids. A total of nine bids were received and publicly opened in the City Clerk's Office on May 28, 2026. After reviewing the bids, Griffith Company with a bid of $5,247,590 was found to have provided the lowest responsive bid from a responsible bidder. Construction is expected to begin in the summer of 2026 and is estimated to take 120 working days to complete.
BACKGROUND
The City of Redondo Beach, in collaboration with the cities of Hermosa Beach, Manhattan Beach and Torrance, along with the Los Angeles County Flood Control District (LACFCD) formed the Beach Cities Watershed Management Group to develop an EWMP to comply with the municipal separate storm sewer system (MS4) permit requirements.? The EWMP defined a set of projects and activities each jurisdiction would undertake to reduce pollution entering the ocean in compliance with standards set by the Regional Water Quality Control Board. The City Council?approved the first EWMP on June 16, 2015 and approved the updated EWMP on June 8, 2021. The updated EWMP includes the Fulton Project as a priority regional project for reducing the potential for pollutants being discharged into the Santa Monica Bay.
Fulton Playfield is an open green space ...