File #: 24-1242    Name:
Type: Consent Item Status: Agenda Ready
File created: 7/17/2024 In control: City Council
On agenda: 7/30/2024 Final action:
Title: APPROVE THE PLANS AND SPECIFICATIONS FOR THE NORTH PIER PARKING STRUCTURE REPAIRS PROJECT, JOB NO. 70610, AND AUTHORIZE THE CITY CLERK TO ADVERTISE THE PROJECT FOR COMPETITIVE BIDS APPROVE THE SECOND AMENDMENT TO THE AGREEMENT FOR CONSULTING SERVICES BETWEEN THE CITY OF REDONDO BEACH AND WALKER PARKING CONSULTANTS/ENGINEERS, INC. TO INCREASE THE AMOUNT BY $65,500 FOR ADDITIONAL CONSULTING SERVICES FOR A NEW NOT TO EXCEED TOTAL OF $629,500 AND EXTEND THE TERM TO SEPTEMBER 5, 2025
Attachments: 1. Administrative Report, 2. 1- CEQA, 3. 2- CDP Exemption, 4. Second_Amendment_to_Walker_Agreement_signed, 5. Certificate of Insurance
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To: MAYOR AND CITY COUNCIL
From: ANDREW WINJE, PUBLIC WORKS DIRECTOR

TITLE
title
APPROVE THE PLANS AND SPECIFICATIONS FOR THE NORTH PIER PARKING STRUCTURE REPAIRS PROJECT, JOB NO. 70610, AND AUTHORIZE THE CITY CLERK TO ADVERTISE THE PROJECT FOR COMPETITIVE BIDS

APPROVE THE SECOND AMENDMENT TO THE AGREEMENT FOR CONSULTING SERVICES BETWEEN THE CITY OF REDONDO BEACH AND WALKER PARKING CONSULTANTS/ENGINEERS, INC. TO INCREASE THE AMOUNT BY $65,500 FOR ADDITIONAL CONSULTING SERVICES FOR A NEW NOT TO EXCEED TOTAL OF $629,500 AND EXTEND THE TERM TO SEPTEMBER 5, 2025
end

EXECUTIVE SUMMARY
In September 2022, the City Council approved the First Amendment to the Agreement for Consulting Services with Walker Parking Consultants/Engineers, Inc. (Walker) for additional consulting services to obtain a geotechnical report for the existing soils conditions and to evaluate the existing foundations in order to identify required information for the final design of the seismic strengthening, and non-seismic rehabilitation, of the North Pier Parking Structure. The First Amendment also included consulting services for the design phase (design plans, construction document preparation) and construction support phase (contract administration, construction observations, and additional materials testing) for the seismic strengthening of the North Pier Parking Structure and the next phase of non-seismic rehabilitation work for the North and South Pier Parking Structures.

Walker prepared the plans and specifications for the seismic strengthening and the non-seismic rehabilitation of the North Pier Parking Structures, and these plans were then sent to the City's Community Development Department (Building Division) for plan check review.

The plans have been approved by the Building Division for permits with the condition of a deferred submittal of an accessibility code complaint final inspection report, certified by a Certified Access Specialist (CASp), prior to the final bui...