Title: PUBLIC HEARING FOR CONSIDERATION OF AN APPEAL OF A DENIAL BY THE PLANNING COMMISSION OF AN EXEMPTION DECLARATION AND VARIANCE TO EXCEED THE 30-FOOT MAXIMUM BUILDING HEIGHT REQUIREMENT FOR THE INSTALLATION OF FOUR (THREE INITIALLY) BULK CRYOGENIC STORAGE TANKS WITH A PROPOSED HEIGHT OF APPROXIMATELY 38 FEET AT AN EXISTING MANUFACTURING FACILITY ON PROPERTY LOCATED WITHIN AN INDUSTRIAL-COMMERCIAL (IC-1) ZONE PROCEDURES Open the public hearing, receive and file all documents and correspondence on the proposed project; Accept all testimony from staff, the applicant, and the public and deliberate; Close the public hearing; Adopt the attached Resolution by title only, and waive further reading. ADOPT BY TITLE ONLY RESOLUTION CC-2610-083 OF THE CITY COUNCIL OF THE CITY OF REDONDO BEACH GRANTING AN APPEAL AND APPROVING AN EXEMPTION DECLARATION AND VARIANCE TO EXCEED THE 30-FOOT MAXIMUM BUILDING HEIGHT REQUIREMENT FOR THE INSTALLATION OF FOUR BULK CRYOGENIC STORAGE TANKS WITH A PROPOSED HEIG...
Attachments: 1. Administrative Report, 2. Attachment 1 - Appeal Application, 3. R 2026-2610-083 GRANTING AN APPEAL AND APPROVING AN EXEMPTION DECLARATION AND VARIANCE TO EXCEED THE 30-FOOT MAX, 4. Attachment 3 - Site Plan, 5. Attachment 4 - Project Renderings, 6. Attachment 5 - Bulk Cryogenic Storage Tank Safety Compliance Presentation, 7. Attachment 6 – August 20, 2026 (Signed), 8. Attachment 7 - Planning Commission Resolution of Denial, 9. Attachment 8 - CEQA Exemption Declaration, 10. Attachment 9 – Public Comments
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To: MAYOR AND CITY COUNCIL
From: MARC WIENER, COMMUNITY DEVELOPMENT DIRECTOR

TITLE
title
PUBLIC HEARING FOR CONSIDERATION OF AN APPEAL OF A DENIAL BY THE PLANNING COMMISSION OF AN EXEMPTION DECLARATION AND VARIANCE TO EXCEED THE 30-FOOT MAXIMUM BUILDING HEIGHT REQUIREMENT FOR THE INSTALLATION OF FOUR (THREE INITIALLY) BULK CRYOGENIC STORAGE TANKS WITH A PROPOSED HEIGHT OF APPROXIMATELY 38 FEET AT AN EXISTING MANUFACTURING FACILITY ON PROPERTY LOCATED WITHIN AN INDUSTRIAL-COMMERCIAL (IC-1) ZONE

PROCEDURES
Open the public hearing, receive and file all documents and correspondence on the proposed project;
Accept all testimony from staff, the applicant, and the public and deliberate;
Close the public hearing;
Adopt the attached Resolution by title only, and waive further reading.

ADOPT BY TITLE ONLY RESOLUTION CC-2610-083 OF THE CITY COUNCIL OF THE CITY OF REDONDO BEACH GRANTING AN APPEAL AND APPROVING AN EXEMPTION DECLARATION AND VARIANCE TO EXCEED THE 30-FOOT MAXIMUM BUILDING HEIGHT REQUIREMENT FOR THE INSTALLATION OF FOUR BULK CRYOGENIC STORAGE TANKS WITH A PROPOSED HEIGHT OF APPROXIMATELY 38 FEET AT AN EXISTING MANUFACTURING FACILITY ON PROPERTY LOCATED WITHIN AN INDUSTRIAL-COMMERCIAL (IC-1) ZONE
end

EXECUTIVE SUMMARY
An application for a Height Variance to exceed the height limit of 30 feet for the installation of four Cryogenic bulk storage tanks with a proposed height of approximately 38 feet at 2477 Manhattan Beach Boulevard was submitted by Michael Gillway on behalf of Impulse Space on June 23, 2026. The tanks will be used to store liquid nitrogen and liquid argon and are constructed with a vacuum-insulated double-wall design. The tanks support the technical requirements of Impulse’s aerospace manufacturing operation and cannot be accommodated at a lesser height without resulting in the fabrication of customized units that do not have the same historical record of safety, or the procurement of significantly smaller tanks that would require ...

Click here for full text