Title: ACCEPT AS COMPLETE THE CITYWIDE CURB RAMP IMPROVEMENTS 2019-2020 PROJECT (FEDERAL HUD B-18-MC-06-0528), AND AUTHORIZE THE CITY ENGINEER TO FILE A NOTICE OF COMPLETION WITH THE LOS ANGELES COUNTY RECORDER AND RELEASE THE FINAL RETENTION PAYMENT OF $25,157.76 TO KALBAN, INC. UPON EXPIRATION OF THE 35-DAY LIEN PERIOD AFTER SAID RECORDATION AND NO CLAIMS BEING FILED UPON THE PROJECT
Attachments: 1. Administrative Report
Date Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

To: MAYOR AND CITY COUNCIL
From: TED SEMAAN, PUBLIC WORKS DIRECTOR

TITLE
title
ACCEPT AS COMPLETE THE CITYWIDE CURB RAMP IMPROVEMENTS 2019-2020 PROJECT (FEDERAL HUD B-18-MC-06-0528), AND AUTHORIZE THE CITY ENGINEER TO FILE A NOTICE OF COMPLETION WITH THE LOS ANGELES COUNTY RECORDER AND RELEASE THE FINAL RETENTION PAYMENT OF $25,157.76 TO KALBAN, INC. UPON EXPIRATION OF THE 35-DAY LIEN PERIOD AFTER SAID RECORDATION AND NO CLAIMS BEING FILED UPON THE PROJECT
end

EXECUTIVE SUMMARY
On September 3, 2019, the City Council awarded Kalban, Inc. a public works contract for $444,103 for the construction of the Citywide Curb Ramp Improvements 2019-2020 Project, Job No. 40399 (Federal HUD B-18-MC-06-0528). The final construction cost was $503,155.29, using $59,052.29 in project contingency funds authorized in the project budget and by Administrative Policy and Procedure No. 14.1 Change Orders. The project is now complete and ready for City Council acceptance and authorization to release the final retention amount of $25,157.76 to the contractor upon expiration of the 35-day lien period and there being no claims filed.

BACKGROUND
On June 18, 2019, the City Council approved the project plans and specifications and authorized the City Clerk to advertise the project for competitive bids.

On July 24, 2019, nine (9) bids were received and publicly opened in the City Clerk's office. After reviewing the bids, Kalban, Inc. with a bid amount of $444,103 was found to be the lowest responsible bidder.

On September 3, 2019, the City Council awarded a public works contract to Kalban, Inc. in the amount of $444,103 for the Citywide Curb Ramp Improvements 2019-2020 Project, Job No. 40399 (Federal HUD B-18-MC-06-0528).

During construction, staff issued one (1) change order in the amount of $59,052.29, bringing the final agreement to $503,155.29, a 13% increase over the original contract amount. The change order allowed for the construction of additional sidewalk, asphalt...